BPA-G1050
1,300 MW hybrid in Deschutes, OR · In queue since November 2023 · Proposed COD December 2028
1,300 MW
Capacity
2
Components
Solar + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
BPA-G1050 is a proposed 1300 MW hybrid solar and battery project located in Deschutes County, Oregon. The development project consists of 650 MW of solar generation paired with 650 MW of battery storage. It is listed in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of November 22, 2023, and a proposed commercial operation date of December 1, 2028.
The interconnection agreement (IA) for BPA-G1050 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the LaPine Substation at 230 kV. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OR
County
Deschutes
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
LaPine Substation at 230 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.