BPA-G1053
1,300 MW storage in Crook, OR · In queue since November 2023 · Proposed COD December 2031
1,300 MW
Capacity
1
Components
Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2031
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-12-01
BPA-G1053 is a proposed 1300 MW battery storage project located in Crook County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of November 22, 2023. The proposed commercial operation date is December 1, 2031.
The interconnection agreement for BPA-G1053 is currently in progress, with the specific study type unknown. The point of interconnection is the Bonanza Substation at 500 kV.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Bonanza Substation at 500 kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G1053