Project BPA-G1065 — Project Summary

Queue ID
BPA-G1065
Capacity
1 MW
Technology
Solar
Status
active
Location
Linn, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BPA-G1065

BPA-G1065BetaActiveSolarBPALBNL

1 MW generation in Linn, OR · In queue since April 2024 · Proposed COD September 2025

1 MW

Capacity

1

Components

Solar

2y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection

Total Duration

1y 5m

Schedule

7 months past proposed COD

In Study38%
Queue EntryApr 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-30

About

BPA-G1065 is a proposed solar generation project with a total capacity of 1 MW, located in Linn County, Oregon. The project is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of April 22, 2024, and a proposed commercial operation date of September 30, 2025.

The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the BPA FEEDER: ALBANY L184, 12kV FEEDER to NETL BYPASS DISCONNECT (POLE SWITCH), with interconnection to occur on the NETL side of the bypass disconnect.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Linn

Grid Region

Mountain West

Market

Developer

Utility

Bonneville Power Administration

Entity

BPA

Service Type

Point of Interconnection

BPA FEEDER: ALBANY L184, 12kV FEEDER to NETL BYPASS DISCONNECT (POLE SWITCH). INTERCONNECTION TO OCCUR ON THE NETL SIDE OF THE BYPASS DISCONNECT

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project BPA-G1065