BPA-G1066
0.4 MW generation in Marion, OR · In queue since April 2024 · Proposed COD June 2024
0.4 MW
Capacity
1
Components
Solar
2y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2 months
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
BPA-G1066 is a proposed solar generation project located in Marion County, Oregon, with a total capacity of 0.4 MW. The project consists of a single 0.4 MW solar component. It is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of April 23, 2024. The proposed commercial operation date is June 1, 2024, and the interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Salem Alumina 115 kV line.
Generated from interconnection queue and public data sources
State
OR
County
Marion
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Salem Alumina 115 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G1066