BPA-G1067
1 MW generation in Adams, WA · In queue since May 2024 · Proposed COD October 2024
1 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
5 months
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-01
BPA-G1067 is a proposed solar generation project located in Adams County, Washington, with a total capacity of 1 MW. The project consists of a single 1 MW solar component. It is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of May 9, 2024, and a proposed commercial operation date of October 1, 2024. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Bell-Boundary #1 230 kV line.
The project is listed under the entity "BPA" in the queue. It is located in the Western region of the United States. The project's status is currently "active" in the interconnection queue.
Generated from interconnection queue and public data sources
State
WA
County
Adams
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Bell-Boundary #1 230 kV line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G1067