BPA-G1068
1 MW generation in Clark, WA · In queue since June 2024 · Proposed COD November 2024
1 MW
Capacity
1
Components
Solar
1y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
5 months
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-07
The proposed project BPA-G1068 is a 1 MW solar generation project located in Clark County, Washington. It is in the Bonneville Power Administration (BPA) interconnection queue, with an entry date of June 21, 2024. The proposed commercial operation date is November 7, 2024.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Sifton 115kV Substation. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
WA
County
Clark
Grid Region
Mountain West
Market
—
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Service Type
—
Point of Interconnection
Sifton 115kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project BPA-G1068