LASSEN LODGE HYDROELECTRIC 2
0.5 MW generation in Tehama, CA · In queue since April 2013 · Proposed COD October 2027
0.5 MW
Capacity
1
Components
Hydro
13y 1m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
14y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–36 months
Proposed COD: 2027-10-15
The Lassen Lodge Hydroelectric 2 project is a proposed 0.5 MW hydroelectric generation project located in Tehama County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-1002, with an entry date of April 30, 2013. The proposed commercial operation date is October 15, 2027, and the Interconnection Agreement (IA) has been executed. The project intends to interconnect to the PG&E grid at the Volta-South 60 kV Line.
The development project consists of a single 0.5 MW hydroelectric component. It is currently listed as "active" in the CAISO queue.
Generated from interconnection queue and public data sources
State
CA
County
Tehama
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Volta-South 60 kV Line
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.