LITTLE BEAR SOLAR 1
20 MW generation in Fresno, CA · In queue since April 2014 · Proposed COD February 2029
20 MW
Capacity
1
Components
Solar
12y 1m
In Queue
IA Executed
IA Status
Signed Nov 2016
Queue → IA
2y 7m
IA → COD
12y 3m
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-01
The Little Bear Solar 1 project is a proposed 20 MW solar generation project located in Fresno County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-1028, with an initial queue entry date of April 30, 2014. The proposed commercial operation date is February 1, 2029.
The project has an executed Interconnection Agreement (IA) dated November 15, 2016. The point of interconnection is the Mendota Substation 115 kV, and the interconnecting utility is PG&E. The project is currently listed as active in the CAISO queue.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Mendota Substation 115 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BIOMSJCT_6_B1
- POI Substation
- Mendota Biomass
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.