ARES NEVADA
44 MW storage in Nye, NV · In queue since April 2014 · Proposed COD January 2027
44 MW
Capacity
1
Components
Other Storage
12y 1m
In Queue
IA Executed
IA Status
Signed Nov 2017
Queue → IA
3y 7m
IA → COD
9y 2m
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-01-08
The ARES NEVADA project is a proposed 44 MW battery storage project located in Nye County, Nevada. The project is being developed within the California Independent System Operator (CAISO) region and interconnected by utility GLW at the Gamebird Substation 230 kV.
The project entered the CAISO interconnection queue as queue ID CAISO-1064 on April 30, 2014. Its proposed commercial operation date is January 8, 2027. An Interconnection Agreement (IA) for the project was executed on November 29, 2017.
Generated from interconnection queue and public data sources
State
NV
County
Nye
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
—
Point of Interconnection
Gamebird Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Gamebird Switchard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.