ALTAMONT MIDWAY LTD
5 MW generation in Alameda, CA · In queue since April 2015 · Proposed COD April 2027
5 MW
Capacity
1
Components
Wind
11y 1m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
12 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-04-28
The Altamont Midway LTD project is a proposed 5 MW wind generation project located in Alameda County, California. The project is being developed within the California Independent System Operator (CAISO) region and interconnects with Pacific Gas & Electric (PGAE) at the Altamont Midway 230 kV point of interconnection.
The project entered the CAISO queue as queue ID CAISO-1096 on April 13, 2015, and has a proposed commercial operation date of April 28, 2027. The interconnection agreement (IA) for the project has been executed. The project has also appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Alameda
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Altamont Midway 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.