LITTLE BEAR 3
20.44 MW generation in Fresno, CA · In queue since April 2015 · Proposed COD February 2029
20.44 MW
Capacity
1
Components
Solar
11y 1m
In Queue
IA Executed
IA Status
Signed Nov 2017
Queue → IA
2y 7m
IA → COD
11y 3m
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-02
The LITTLE BEAR 3 project is a proposed solar generation project located in Fresno County, California, with a total capacity of 20.44 MW. The project is in the CAISO interconnection queue under queue ID CAISO-1127, having entered the queue on April 30, 2015. The proposed commercial operation date is February 2, 2029. An Interconnection Agreement (IA) has been executed for the project on November 28, 2017.
The LITTLE BEAR 3 project is linked to the existing Little Bear 3 operating plant (EIA plant ID 62463). The project will interconnect to the PG&E grid at the Mendota Substation 115kV. The developer is unknown. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Mendota Substation 115kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- LTBERA05_7_N002