LITTLE BEAR 4
103.09 MW generation in Fresno, CA · In queue since April 2015 · Proposed COD February 2029
103.09 MW
Capacity
1
Components
Solar
11y 1m
In Queue
IA Executed
IA Status
Signed Nov 2017
Queue → IA
2y 7m
IA → COD
11y 3m
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2029-02-02
The LITTLE BEAR 4 project is a proposed 103.09 MW solar generation project located in Fresno County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1128, with a queue entry date of April 30, 2015. The proposed commercial operation date is February 2, 2029. The interconnection agreement (IA) for the project was executed on November 29, 2017, and the project's interconnection point is the Mendota Substation 115kV.
The LITTLE BEAR 4 project has been the subject of recent news coverage, with six articles categorized as regulatory, industry, and deals.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Mendota Substation 115kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BIOMSJCT_6_B1
- POI Substation
- Mendota Biomass
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about LITTLE BEAR 4