AGUA CALIENTE SOLAR 2
20 MW generation in Maricopa, AZ · In queue since March 2016 · Proposed COD December 2016
20 MW
Capacity
1
Components
Solar
10y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2016
Total Duration
9 months
Schedule
115 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2016-12-01
The AGUA CALIENTE SOLAR 2 project is a proposed 20 MW solar generation project located in Maricopa County, Arizona. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1222, with a queue entry date of March 8, 2016. The proposed commercial operation date is December 1, 2016.
The interconnection agreement (IA) status is listed as "In Progress (unknown study)". The project's point of interconnection (POI) is the Hoodoo Wash Switchyard 500 kV, and the interconnecting utility is San Diego Gas & Electric (SDGE). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
Hoodoo Wash Switchyard 500 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about AGUA CALIENTE SOLAR 2