DAYLIGHT
610.707 MW hybrid in Kings, CA · In queue since May 2016 · Proposed COD January 2028
610.707 MW
Capacity
2
Components
Solar + Battery
10 years
In Queue
IA Executed
IA Status
Signed Dec 2023
Queue → IA
7y 7m
IA → COD
4y 1m
Total Duration
7y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-01-19
The DAYLIGHT project is a proposed 610.71 MW hybrid solar and battery energy storage project located in Kings County, California. The development project consists of 310.71 MW of solar photovoltaic generation coupled with a 300 MW battery energy storage system. The project is interconnected within the CAISO region and is in the CAISO interconnection queue as queue ID CAISO-1223, with an initial queue entry date of May 2, 2016. The proposed commercial operation date is January 19, 2028.
The interconnection agreement (IA) for the DAYLIGHT project has been executed as of December 18, 2023. The point of interconnection (POI) is the Mustang 230 kV substation. The project has been the subject of recent news coverage, with five articles categorized as industry-related and regulatory.
Generated from interconnection queue and public data sources
State
CA
County
Kings
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Mustang 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- GOLDTREE_1_N001
- POI Substation
- Mustang Substation (75)
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26