DAGGETT SOLAR 3 (CAISO-1314) — Project Summary

Queue ID
CAISO-1314
Capacity
521.88 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
IA Executed

DAGGETT SOLAR 3

CAISO-1314BetaActiveSolarBatteryCAISOLBNL + Live

521.88 MW hybrid in San Bernardino, CA · In queue since May 2016 · Proposed COD August 2023

521.88 MW

Capacity

2

Components

Solar + Battery

10 years

In Queue

IA Executed

IA Status

Signed Dec 2018

Interconnection

Queue → IA

2y 7m

IA → COD

4y 8m

Total Duration

2y 7m

Schedule

33 months past proposed COD

Construction75%
Queue EntryMay 2, 2016

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementDec 6, 2018

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2023-08-06

Technology
Solar313.88 MW · 60%
Battery208 MW · 40%
About

The Daggett Solar 3 project is a proposed 521.88 MW hybrid solar and battery energy storage project located in San Bernardino County, California. The development project consists of a 313.88 MW solar component and a 208 MW battery energy storage component. The project is in the CAISO interconnection queue (queue ID CAISO-1314) with an interconnection queue entry date of May 2, 2016, and a proposed commercial operation date of August 6, 2023.

The project's interconnection agreement (IA) was executed on December 6, 2018. The point of interconnection is the Kramer Substation 230kV. Daggett Solar 3 has been the subject of recent news coverage, with seven articles appearing in industry, deals, and grid-related publications.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

San Bernardino

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

SCE

Entity

CAISO

Service Type

Point of Interconnection

Kramer Substation 230kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
KRAMER_1_N001
POI Substation
Kramer Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.