TAHOE
300 MW storage in Clark, NV · In queue since May 2016 · Proposed COD May 2026
300 MW
Capacity
1
Components
Battery
10 years
In Queue
IA Executed
IA Status
Signed Jul 2018
Queue → IA
2y 2m
IA → COD
7y 10m
Total Duration
2y 2m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-01
The proposed TAHOE project is a 300 MW battery storage development in Clark County, Nevada. Interconnecting to the Southern California Edison (SCE) owned Eldorado Bus 230kV, it is located within the California Independent System Operator (CAISO) region and has queue ID CAISO-1339. The project entered the CAISO queue on May 2, 2016, with a proposed commercial operation date of May 1, 2026.
The interconnection agreement (IA) for the TAHOE project was executed on July 23, 2018. The project currently has an active status within the CAISO queue and has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
SCE owned Eldorado Bus 230kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26