SANDSTORM WIND POWER
150 MW hybrid in Riverside, CA · In queue since October 2006 · Proposed COD February 2030
150 MW
Capacity
2
Components
Wind + Battery
19y 7m
In Queue
IA Executed
IA Status
Signed Oct 2014
Queue → IA
8 years
IA → COD
15y 4m
Total Duration
8 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–36 months
Proposed COD: 2030-02-01
The Sandstorm Wind Power project is a proposed 150 MW hybrid wind and battery energy storage project located in Riverside County, California. The project consists of a 60 MW wind farm coupled with a 90 MW battery energy storage system. It is interconnected to the Devers Substation 220 kV.
The project is listed in the CAISO interconnection queue as queue ID CAISO-138, with an original queue entry date of October 23, 2006. The proposed commercial operation date is February 1, 2030. The project has an Interconnection Agreement (IA) executed on October 9, 2014. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Devers Substation 220 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- GARNET_7_N006
- POI Substation
- Devers Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.