REDUX SOLAR
189.49 MW hybrid in Fresno, CA · In queue since May 2017 · Proposed COD June 2026
189.49 MW
Capacity
2
Components
Solar + Battery
9 years
In Queue
IA Executed
IA Status
Signed Dec 2021
Queue → IA
4y 7m
IA → COD
4y 6m
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-06-01
The REDUX SOLAR project is a proposed hybrid solar and battery energy storage project located in Fresno County, California. The development project, with a total capacity of 189.49 MW, consists of a 128.24 MW solar array coupled with a 61.25 MW battery energy storage system. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1389, with an interconnection queue date of May 1, 2017.
The proposed commercial operation date for REDUX SOLAR is June 1, 2026. The project has an executed Interconnection Agreement (IA), which was finalized on December 28, 2021. The point of interconnection (POI) for the project is the Gates 230 kV substation. The project is currently listed as active in the CAISO queue.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Gates 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- FIFTHS_7_N003
- POI Substation
- Gates Substation