STARLIGHT SOLAR
37.4 MW hybrid in San Diego, CA · In queue since May 2017 · Proposed COD April 2027
37.4 MW
Capacity
2
Components
Solar + Battery
9 years
In Queue
IA Executed
IA Status
Signed Apr 2021
Queue → IA
3y 11m
IA → COD
6 years
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-04-30
The STARLIGHT SOLAR project is a proposed 37.4 MW hybrid solar and battery energy storage project located in San Diego County, California. The development project consists of a 20 MW solar array coupled with a 17.4 MW battery energy storage system. The project is interconnected to the San Diego Gas & Electric (SDGE) grid at the Boulevard East Substation 69 kV.
The project is listed in the CAISO interconnection queue as queue ID CAISO-1432, with an initial queue entry date of May 1, 2017. The proposed commercial operation date is April 30, 2027. The project's Interconnection Agreement (IA) has been executed as of April 12, 2021. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
San Diego
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
Boulevard East Substation 69 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Boulevard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about STARLIGHT SOLAR