JANUS
163.54 MW hybrid in Colusa, CA · In queue since April 2018 · Proposed COD March 2027
163.54 MW
Capacity
2
Components
Solar + Battery
8y 1m
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-03-01
The JANUS project is a proposed 163.54 MW hybrid solar and battery energy storage project located in Colusa County, California. The development project consists of an 83.54 MW solar component and an 80 MW battery energy storage system. It is interconnected to the PG&E utility network within the CAISO region.
The project, identified as CAISO-1455 in the CAISO interconnection queue, entered the queue on April 16, 2018, and has a proposed commercial operation date of March 1, 2027. The interconnection agreement (IA) for the project has been executed. The point of interconnection (POI) is the Cortina 60 kV substation. The project has been mentioned in recent news coverage related to the energy industry.
Generated from interconnection queue and public data sources
State
CA
County
Colusa
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Cortina 60 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CORTINA_1_N106
- POI Substation
- Cortina Substation