LAS CAMAS 3
202.5 MW hybrid in Merced, CA · In queue since April 2018 · Proposed COD December 2027
202.5 MW
Capacity
2
Components
Solar + Battery
8y 1m
In Queue
IA Executed
IA Status
Signed Mar 2022
Queue → IA
3y 11m
IA → COD
5y 9m
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-31
The Las Camas 3 project is a proposed 202.5 MW hybrid solar and battery energy storage project located in Merced County, California. The project consists of a 102.5 MW solar array coupled with a 100 MW battery energy storage system. It is interconnected within the California Independent System Operator (CAISO) queue as queue ID CAISO-1456. The project entered the queue on April 16, 2018, and has a proposed commercial operation date of December 31, 2027.
The interconnection agreement (IA) for Las Camas 3 has been executed as of March 28, 2022. The point of interconnection (POI) is the Los Banos 230 kV substation. The project is currently listed as active in the CAISO interconnection queue. Recent news coverage has discussed the project's progress.
Generated from interconnection queue and public data sources
State
CA
County
Merced
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Los Banos 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SNTANLA_6_N001
- POI Substation
- Los Banos Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about LAS CAMAS 3