MILPA POWER BANK
3 MW storage in Santa Clara, CA · In queue since April 2018 · Proposed COD April 2025
3 MW
Capacity
1
Components
Battery
8y 1m
In Queue
System Impact Study
IA Status
COD target: 2025
Total Duration
7 years
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-04-29
The proposed MILPA POWER BANK project is a 3 MW battery storage development in Santa Clara County, California. Interconnection is requested through the CAISO queue (CAISO-1457) with Pacific Gas & Electric (PGAE) at the Los Esteros 115 kV point of interconnection. The project entered the CAISO queue on April 16, 2018, and has a proposed commercial operation date of April 29, 2025. Its interconnection status is currently in the System Impact Study phase.
The project consists of a single 3 MW battery component. The MILPA POWER BANK project has appeared in recent news coverage regarding energy storage projects in California.
Generated from interconnection queue and public data sources
State
CA
County
Santa Clara
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Los Esteros 115 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LECEFGT2_7_B1
- POI Substation
- Los Esteros Substation