JASMINE
141.161 MW hybrid in Kern, CA · In queue since April 2018 · Proposed COD August 2026
141.161 MW
Capacity
2
Components
Solar + Battery
8y 1m
In Queue
IA Executed
IA Status
Signed Jun 2020
Queue → IA
2y 2m
IA → COD
6y 2m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2026-08-31
The JASMINE project is a proposed 141.16 MW hybrid solar and battery energy storage project located in Kern County, California. The development project consists of a 71.16 MW solar component and a 70 MW battery energy storage component. It is listed in the CAISO interconnection queue as project CAISO-1499, with an initial queue entry date of April 16, 2018.
The proposed commercial operation date for the JASMINE project is August 31, 2026. The project has an active interconnection agreement, which was executed on June 5, 2020. The point of interconnection is the Lakeview 70 kV substation.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Lakeview 70 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BOTTLERK_7_N001
- POI Substation
- Lakeview