ARIDA SOLAR FARM
740 MW hybrid in Clark, NV · In queue since April 2018 · Proposed COD September 2027
740 MW
Capacity
2
Components
Solar + Battery
8y 1m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
9y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-15
The Arida Solar Farm is a proposed 740 MW hybrid solar and battery project located in Clark County, Nevada. The development project consists of 370 MW of solar photovoltaic generation paired with 370 MW of battery energy storage. The project is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-1522, with an interconnection queue entry date of April 16, 2018.
The proposed commercial operation date is September 15, 2027. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Mohave Substation 500kV, and the interconnecting utility is Southern California Edison (SCE). The Arida Solar Farm has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Mohave Substation 500kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SOPOINT_LNODE-2
- POI Substation
- Mohave Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.