IRVING STORAGE
782.79 MW storage in Monterey, CA · In queue since May 2019 · Proposed COD November 2025
782.79 MW
Capacity
1
Components
Battery
7 years
In Queue
IA Executed
IA Status
Signed Jul 2021
Queue → IA
2y 2m
IA → COD
4y 4m
Total Duration
2y 2m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-11-30
The Irving Storage project is a proposed 782.79 MW battery storage project located in Monterey County, California. Interconnecting to PG&E via the Moss Landing 500 kV point of interconnection, the project is in the CAISO interconnection queue as queue ID CAISO-1539, with an initial queue entry date of May 7, 2019. The developer anticipates a commercial operation date of November 30, 2025.
The project's interconnection agreement was executed on July 12, 2021. The Irving Storage project has been the subject of recent news coverage, with at least 10 articles appearing in the press.
Generated from interconnection queue and public data sources
State
CA
County
Monterey
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Moss Landing 500 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about IRVING STORAGE