DYNAMO SOLAR (CAISO-1565) — Project Summary

Queue ID
CAISO-1565
Capacity
24.5 MW
Technology
Solar
Status
active
Location
Napa, CA
Region
CAISO
Developer
IA Status
IA Executed

DYNAMO SOLAR

CAISO-1565BetaActiveSolarCAISOLBNL + Live

24.5 MW generation in Napa, CA · In queue since April 2019 · Proposed COD July 2027

24.5 MW

Capacity

1

Components

Solar

7y 1m

In Queue

IA Executed

IA Status

Signed Sep 2021

Interconnection

Queue → IA

2y 5m

IA → COD

5y 10m

Total Duration

2y 5m

Construction75%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementSep 13, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-07-16

About

The Dynamo Solar project is a proposed 24.5 MW solar generation project located in Napa County, California. The project is interconnected within the CAISO region and is listed in the CAISO interconnection queue as entry CAISO-1565, with a queue entry date of April 15, 2019. The proposed commercial operation date is July 16, 2027.

The project's Interconnection Agreement (IA) was executed on September 13, 2021. The point of interconnection is the Tulucay 60 kV substation. The Dynamo Solar project is linked to the existing Dynamo Solar LLC operating plant (EIA plant ID 68528). The project has appeared in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Napa

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

PGAE

Entity

CAISO

Service Type

Point of Interconnection

Tulucay 60 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_NP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
TULUCAY_6_N001
POI Substation
Tulucay Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.