DYNAMO SOLAR
24.5 MW generation in Napa, CA · In queue since April 2019 · Proposed COD July 2027
24.5 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
Signed Sep 2021
Queue → IA
2y 5m
IA → COD
5y 10m
Total Duration
2y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-07-16
The Dynamo Solar project is a proposed 24.5 MW solar generation project located in Napa County, California. The project is interconnected within the CAISO region and is listed in the CAISO interconnection queue as entry CAISO-1565, with a queue entry date of April 15, 2019. The proposed commercial operation date is July 16, 2027.
The project's Interconnection Agreement (IA) was executed on September 13, 2021. The point of interconnection is the Tulucay 60 kV substation. The Dynamo Solar project is linked to the existing Dynamo Solar LLC operating plant (EIA plant ID 68528). The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Napa
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Tulucay 60 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- TULUCAY_6_N001
- POI Substation
- Tulucay Substation