KINGSROAD HYBRID SOLAR
203.56 MW hybrid in Kern, CA · In queue since April 2019 · Proposed COD December 2028
203.56 MW
Capacity
2
Components
Solar + Battery
7y 1m
In Queue
IA Executed
IA Status
Signed Feb 2023
Queue → IA
3y 10m
IA → COD
5y 10m
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-01
The KINGSROAD HYBRID SOLAR project is a proposed 203.56 MW hybrid solar and battery energy storage project located in Kern County, California. The development project consists of 101.78 MW of solar photovoltaic generation paired with 101.78 MW of battery energy storage. The project is interconnected within the California Independent System Operator (CAISO) queue as queue ID CAISO-1587, having entered the queue on April 15, 2019.
The proposed commercial operation date is December 1, 2028. The project has an executed Interconnection Agreement (IA), dated February 14, 2023, and will interconnect at the Arco 230 kV point of interconnection. The project is within the Pacific Gas & Electric (PGAE) service area.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Arco 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- AGRICO_7_B1
- POI Substation
- Agrico
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about KINGSROAD HYBRID SOLAR