AVOCET STORAGE
200 MW storage in Los Angeles, CA · In queue since April 2019 · Proposed COD April 2026
200 MW
Capacity
1
Components
Battery
7y 1m
In Queue
IA Executed
IA Status
Signed Jun 2021
Queue → IA
2y 2m
IA → COD
4y 10m
Total Duration
2y 2m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-04-15
The AVOCET STORAGE project is a proposed 200 MW battery energy storage system located in Los Angeles County, California. The project is interconnected within the CAISO region, with Southern California Edison (SCE) as the utility. It entered the CAISO queue as queue ID CAISO-1608 on April 15, 2019, and has a proposed commercial operation date of April 15, 2026. The project's interconnection agreement (IA) was executed on June 18, 2021.
The AVOCET STORAGE project has been the subject of recent news coverage, with at least eight articles appearing in categories such as grid development, industry trends, regulatory matters, and business deals. The point of interconnection is the Hinson Substation at 230kV.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Hinson Substation 230kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HINSON_2_B1
- POI Substation
- Hinson Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.