COMMERCE ENERGY STORAGE
250 MW storage in Los Angeles, CA · In queue since April 2019 · Proposed COD June 2026
250 MW
Capacity
1
Components
Battery
7y 1m
In Queue
IA Executed
IA Status
Signed Jan 2022
Queue → IA
2y 9m
IA → COD
4y 5m
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-06-01
The Commerce Energy Storage project is a proposed 250 MW battery storage development in Los Angeles County, California. The project is located in the CAISO region and interconnects to Southern California Edison (SCE) at the Laguna Bell Substation 230kV. It entered the CAISO interconnection queue as queue ID CAISO-1611 on April 15, 2019, with a proposed commercial operation date of June 1, 2026. An Interconnection Agreement (IA) was executed on January 12, 2022.
The project consists of 250 MW of battery storage capacity. The Commerce Energy Storage project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Laguna Bell Substation 230kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LAGUBELL_6_N005
- POI Substation
- Laguna Bell Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.