KESTREL STORAGE
200 MW storage in Los Angeles, CA · In queue since April 2019 · Proposed COD February 2027
200 MW
Capacity
1
Components
Battery
7y 1m
In Queue
IA Executed
IA Status
Signed Jun 2021
Queue → IA
2y 2m
IA → COD
5y 8m
Total Duration
2y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-02-28
The KESTREL STORAGE project is a proposed 200 MW battery storage project located in Los Angeles County, California. The project is being developed within the CAISO interconnection queue under queue ID CAISO-1615. Its queue entry date is April 15, 2019, and the proposed commercial operation date is February 28, 2027. An Interconnection Agreement (IA) has been executed for the project on June 18, 2021. The point of interconnection is the Walnut Substation at 220kV, and the utility is SCE.
The KESTREL STORAGE project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Walnut Substation 220kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WALNUTEC_1_UNIT3GNODE
- POI Substation
- Walnut Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about KESTREL STORAGE