ANGELENO SOLAR FARM
2,300 MW hybrid in Los Angeles, CA · In queue since April 2019 · Proposed COD December 2028
2,300 MW
Capacity
2
Components
Solar + Battery
7y 1m
In Queue
IA Executed
IA Status
Signed Jan 2022
Queue → IA
2y 9m
IA → COD
6y 11m
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-31
The Angeleno Solar Farm is a proposed 2300 MW hybrid solar and battery project located in Los Angeles County, California. The development project, which has appeared in recent news, consists of 1150 MW of solar generation and 1150 MW of battery energy storage. It is listed in the CAISO interconnection queue as CAISO-1625, with an entry date of April 15, 2019, and a proposed commercial operation date of December 31, 2028.
The project's interconnection agreement (IA) was executed on January 28, 2022. The point of interconnection is the Vincent Substation 500kV.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Vincent Substation 500kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- VINCENT_2_N101
- POI Substation
- Vincent Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.