ARIDA 2 SOLAR FARM
1,400 MW hybrid in Clark, NV · In queue since April 2019 · Proposed COD May 2029
1,400 MW
Capacity
2
Components
Solar + Battery
7y 1m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
10y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-31
The ARIDA 2 SOLAR FARM is a proposed 1400 MW hybrid solar and battery project located in Clark County, Nevada. The project, which consists of 700 MW of solar generation and 700 MW of battery storage, is interconnected to Southern California Edison (SCE) within the California Independent System Operator (CAISO) region.
The project is listed in the CAISO interconnection queue as entry CAISO-1647, with an interconnection queue entry date of April 15, 2019. The proposed commercial operation date is May 31, 2029. The project's interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Mohave Substation 500kV.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Mohave Substation 500kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SOPOINT_LNODE-2
- POI Substation
- Mohave Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.