ARIDA 2 SOLAR FARM (CAISO-1647) — Project Summary

Queue ID
CAISO-1647
Capacity
1400 MW
Technology
Solar+Battery
Status
active
Location
Clark, NV
Region
CAISO
Developer
IA Status
System Impact Study

ARIDA 2 SOLAR FARM

CAISO-1647BetaActiveSolarBatteryCAISOLBNL + Live

1,400 MW hybrid in Clark, NV · In queue since April 2019 · Proposed COD May 2029

1,400 MW

Capacity

2

Components

Solar + Battery

7y 1m

In Queue

System Impact Study

IA Status

COD target: 2029

Interconnection

Total Duration

10y 1m

Impact Study25%
Queue EntryApr 15, 2019

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-31

Technology
Solar700 MW · 50%
Battery700 MW · 50%
About

The ARIDA 2 SOLAR FARM is a proposed 1400 MW hybrid solar and battery project located in Clark County, Nevada. The project, which consists of 700 MW of solar generation and 700 MW of battery storage, is interconnected to Southern California Edison (SCE) within the California Independent System Operator (CAISO) region.

The project is listed in the CAISO interconnection queue as entry CAISO-1647, with an interconnection queue entry date of April 15, 2019. The proposed commercial operation date is May 31, 2029. The project's interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Mohave Substation 500kV.

Generated from interconnection queue and public data sources

Project Details

State

NV

County

Clark

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

SCE

Entity

CAISO

Service Type

Point of Interconnection

Mohave Substation 500kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SOPOINT_LNODE-2
POI Substation
Mohave Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.