CIMARRON WIND
352.5 MW generation in Tecate, MX · In queue since April 2019 · Proposed COD December 2025
352.5 MW
Capacity
1
Components
Wind
7y 1m
In Queue
IA Executed
IA Status
Signed Dec 2023
Queue → IA
4y 8m
IA → COD
2 years
Total Duration
4y 8m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2025-12-31
CIMARRON WIND is a proposed wind generation project with a total capacity of 352.5 MW, located in Tecate County, Mexico. Interconnection is planned with San Diego Gas & Electric (SDGE) via the East County Substation 230 kV. The project is listed in the California Independent System Operator (CAISO) queue as entry CAISO-1660, with a queue entry date of April 15, 2019, and a proposed commercial operation date of December 31, 2025. The interconnection agreement (IA) has been executed as of December 21, 2023.
The CIMARRON WIND project has been the subject of recent news coverage, with seven articles categorized as deals, industry, and development.
Generated from interconnection queue and public data sources
State
MX
County
Tecate
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
East County Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26