CONAWAY HYBRID POWER PLANT
169.807 MW hybrid in Yolo, CA · In queue since April 2020 · Proposed COD January 2023
169.807 MW
Capacity
2
Components
Solar + Battery
6y 1m
In Queue
System Impact Study
IA Status
COD target: 2023
Total Duration
2y 9m
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-01-01
The Conaway Hybrid Power Plant is a proposed project located in Yolo County, California, within the CAISO region. This hybrid project, consisting of both solar and battery components, has a total capacity of 169.81 MW. Specifically, it includes 85.0 MW of solar generation and 84.81 MW of battery energy storage.
The project, identified as CAISO-1687 in the CAISO interconnection queue, entered the queue on April 15, 2020, with a proposed commercial operation date of January 1, 2023. The interconnection utility is PG&E. As of the latest data, the project's interconnection status is in the System Impact Study phase, and the point of interconnection is the Woodland-Davis 115 kV Line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CA
County
Yolo
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Woodland-Davis 115 kV Line
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.