GONZAGA HYBRID
115.39 MW hybrid in Merced, CA · In queue since April 2020 · Proposed COD March 2026
115.39 MW
Capacity
2
Components
Wind + Battery
6y 1m
In Queue
IA Executed
IA Status
COD target: 2026
Total Duration
5y 11m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–36 months
Proposed COD: 2026-03-31
The Gonzaga Hybrid project is a proposed wind and battery energy storage project located in Merced County, California. The development project, with a total capacity of 115.39 MW, consists of a 60.45 MW wind farm and a 54.94 MW battery energy storage system.
The project is in the CAISO interconnection queue as entry CAISO-1718, with a queue entry date of April 15, 2020. The proposed commercial operation date is March 31, 2026, and the Interconnection Agreement (IA) has been executed. The point of interconnection is the Los Banos 70 kV substation. The interconnecting utility is PG&E.
Generated from interconnection queue and public data sources
State
CA
County
Merced
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Los Banos 70 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SNTANLA_6_N001
- POI Substation
- Los Banos Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.