PUFF HYBRID SOLAR
203.6 MW hybrid in Kern, CA · In queue since April 2020 · Proposed COD September 2030
203.6 MW
Capacity
2
Components
Solar + Battery
6y 1m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
10y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-09-01
The PUFF HYBRID SOLAR project is a proposed 203.6 MW hybrid solar and battery energy storage project in Kern County, California. The project consists of 101.8 MW of solar generation paired with 101.8 MW of battery storage. It is located within the CAISO region and is interconnected to the PGAE utility grid at the Arco 230 kV point of interconnection.
The project, identified as CAISO-1740 in the CAISO interconnection queue, entered the queue on April 15, 2020. Its proposed commercial operation date is September 1, 2030. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Arco 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- AGRICO_7_B1
- POI Substation
- Agrico
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about PUFF HYBRID SOLAR