CRYSTAL FLATS
154.856 MW hybrid in Kern, CA · In queue since April 2020 · Proposed COD December 2030
154.856 MW
Capacity
2
Components
Solar + Battery
6y 1m
In Queue
IA Executed
IA Status
Signed Jan 2024
Queue → IA
3y 9m
IA → COD
6y 11m
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2030-12-26
The Crystal Flats project is a proposed 154.86 MW hybrid solar and battery energy storage development in Kern County, California. The project, located within the CAISO region and interconnected with PG&E, consists of a 103.45 MW solar array and a 51.4 MW battery energy storage system. It is listed in the CAISO interconnection queue as CAISO-1744, with an entry date of April 15, 2020, and a proposed commercial operation date of December 26, 2030.
The Crystal Flats project has an Interconnection Agreement (IA) executed on January 9, 2024. The point of interconnection is the Lamont 115 kV substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Lamont 115 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about CRYSTAL FLATS