WINDWALKER OFFSHORE (CAISO-1750) — Project Summary

Queue ID
CAISO-1750
Capacity
1028.94 MW
Technology
Offshore Wind
Status
active
Location
San Luis Obispo, CA
Region
CAISO
Developer
IA Status
IA Executed

WINDWALKER OFFSHORE

CAISO-1750BetaActiveOffshore WindCAISOLBNL + Live

1,028.94 MW generation in San Luis Obispo, CA · In queue since April 2020 · Proposed COD February 2028

1,028.94 MW

Capacity

1

Components

Offshore Wind

6y 1m

In Queue

IA Executed

IA Status

Signed Jan 2023

Interconnection

Queue → IA

2y 9m

IA → COD

5y 1m

Total Duration

2y 9m

Construction75%
Queue EntryApr 15, 2020

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementJan 8, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 36–60 months

Commercial Operation

Proposed COD: 2028-02-12

About

The WINDWALKER OFFSHORE project is a proposed 1028.94 MW offshore wind generation project located in San Luis Obispo County, California. The project is in the CAISO interconnection queue as entry CAISO-1750, with a queue entry date of April 15, 2020, and a proposed commercial operation date of February 12, 2028. The interconnecting utility is PG&E.

The project's Interconnection Agreement (IA) was executed on January 8, 2023. The point of interconnection (POI) is the Diablo Canyon 500 kV substation. The WINDWALKER OFFSHORE project has been mentioned in recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

San Luis Obispo

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

PGAE

Entity

CAISO

Service Type

Point of Interconnection

Diablo Canyon 500 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
DIABLO2_7_B1
POI Substation
Diablo Canyon

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about WINDWALKER OFFSHORE