WINSTON HYBRID PV AND BESS
306 MW hybrid in Kern, CA · In queue since April 2020 · Proposed COD December 2028
306 MW
Capacity
2
Components
Solar + Battery
6y 1m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
8y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-10
The Winston Hybrid PV and BESS project is a proposed 306 MW hybrid solar and battery energy storage system development in Kern County, California. The project consists of a 204 MW solar photovoltaic array coupled with a 102 MW battery energy storage system. It is located within the California Independent System Operator (CAISO) region and is interconnected to the PG&E utility grid at the Midway 115 kV point of interconnection.
The project, identified as CAISO-1751 in the CAISO interconnection queue, entered the queue on April 15, 2020, and has a proposed commercial operation date of December 10, 2028. The Interconnection Agreement (IA) for the project has been executed. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Midway 115 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MIDWAY_1_N084
- POI Substation
- Midway Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about WINSTON HYBRID PV AND BESS