OVERNIGHT SOLAR (CAISO-1774) — Project Summary

Queue ID
CAISO-1774
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
San Bernardino, CA
Region
CAISO
Developer
IA Status
IA Executed

OVERNIGHT SOLAR

CAISO-1774BetaActiveSolarBatteryCAISOLBNL + Live

300 MW hybrid in San Bernardino, CA · In queue since April 2020 · Proposed COD May 2027

300 MW

Capacity

2

Components

Solar + Battery

6y 1m

In Queue

IA Executed

IA Status

Signed Feb 2024

Status
as of 3y 5m ago
Project statusOperationalSolarPACES · 2022-12-04
Interconnection

Queue → IA

3y 10m

IA → COD

3y 3m

Total Duration

3y 10m

Construction75%
Queue EntryApr 15, 2020

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementFeb 17, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2027-05-01

Technology
Solar150 MW · 50%
Battery150 MW · 50%
About

OVERNIGHT SOLAR is a proposed hybrid solar and battery project located in San Bernardino County, California, with a total capacity of 300 MW. The project consists of 150 MW of solar generation and a 150 MW battery energy storage system. It is listed in the CAISO interconnection queue as entry CAISO-1774, with a queue entry date of April 15, 2020, and a proposed commercial operation date of May 1, 2027. The project's point of interconnection is the Kramer Substation 230kV, and the interconnecting utility is Southern California Edison (SCE).

The project's interconnection agreement (IA) has been executed as of February 17, 2024. Recent news coverage indicates interest in the project, with nine articles appearing in industry publications.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

San Bernardino

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

SCE

Entity

CAISO

Service Type

Point of Interconnection

Kramer Substation 230kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
KRAMER_1_N001
POI Substation
Kramer Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.