BELLEFIELD 3 SOLAR FARM
300 MW hybrid in Kern, CA · In queue since April 2020 · Proposed COD April 2027
300 MW
Capacity
2
Components
Solar + Battery
6y 1m
In Queue
IA Executed
IA Status
Signed Jun 2023
Queue → IA
3y 2m
IA → COD
3y 10m
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-04-01
The Bellefield 3 Solar Farm is a proposed 300 MW hybrid solar and battery energy storage project in Kern County, California. The development project, which consists of 150 MW of solar photovoltaic generation and 150 MW of battery storage, is located within the California Independent System Operator (CAISO) region and interconnects with Southern California Edison (SCE) at the Windhub Substation 230kV.
The project, identified by queue ID CAISO-1779, entered the CAISO interconnection queue on April 15, 2020, and has a proposed commercial operation date of April 1, 2027. An Interconnection Agreement (IA) for the project was executed on June 28, 2023. The Bellefield 3 Solar Farm project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Windhub Substation 230kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ALTA6B2_7_N003
- POI Substation
- Windhub Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09