KEYHOLE WIND
100 MW generation in Kern, CA · In queue since April 2020 · Proposed COD June 2028
100 MW
Capacity
1
Components
Wind
6y 1m
In Queue
IA Executed
IA Status
Signed May 2022
Queue → IA
2y 1m
IA → COD
6y 1m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2028-06-28
The Keyhole Wind project is a proposed 100 MW wind generation project located in Kern County, California. The project is listed in the CAISO interconnection queue as entry CAISO-1784, with a queue entry date of April 15, 2020. Southern California Edison (SCE) is the utility.
The proposed commercial operation date for Keyhole Wind is June 28, 2028. The project's interconnection agreement (IA) has been executed as of May 23, 2022. Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Whirlwind Substation 230kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ASTORIA2_7_N001
- POI Substation
- Whirlwind Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.