REXFORD 2 SOLAR FARM
400 MW hybrid in Tulare, CA · In queue since April 2020 · Proposed COD July 2027
400 MW
Capacity
2
Components
Solar + Battery
6y 1m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
The REXFORD 2 SOLAR FARM is a proposed 400 MW hybrid solar and battery energy storage project located in Tulare County, California. The development project, consisting of 200 MW of solar photovoltaic generation and 200 MW of battery storage, is interconnected to the CAISO grid at the Vestal Substation 230kV. The project's queue ID is CAISO-1789, and it entered the CAISO interconnection queue on April 15, 2020, with a proposed commercial operation date of July 1, 2027. The project's interconnection status is currently in the System Impact Study phase.
The proposed project is in the service territory of Southern California Edison (SCE). Recent news coverage has highlighted the project, with articles appearing in grid and industry publications.
Generated from interconnection queue and public data sources
State
CA
County
Tulare
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Vestal Substation 230kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- REXFRD_2_RSFBX2-APND
- POI Substation
- Vestal Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about REXFORD 2 SOLAR FARM