TOLENAS
417.349 MW storage in Solano, CA · In queue since April 2021 · Proposed COD February 2031
417.349 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-18
The TOLENAS project is a proposed 417.35 MW battery storage project located in Solano County, California. The project, under development in the CAISO region, entered the CAISO interconnection queue as queue ID CAISO-1842 on April 15, 2021. Pacific Gas and Electric (PGAE) is the utility.
The proposed commercial operation date (COD) for the TOLENAS project is February 18, 2031. The project's interconnection status is currently in the System Impact Study phase, and it will connect to the Lambie 230 kV point of interconnection. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CA
County
Solano
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Lambie 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LAMBGT1_7_B1
- POI Substation
- Lambie Substation