BRUSHY
400 MW storage in Solano, CA · In queue since April 2021 · Proposed COD February 2031
400 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-18
The BRUSHY project is a proposed 400 MW battery storage project located in Solano County, California. The project is interconnected to the CAISO grid at the Lambie 230 kV point of interconnection and is in the CAISO interconnection queue as entry CAISO-1843, with a queue entry date of April 15, 2021.
The project's interconnection status is currently in the System Impact Study phase, with a proposed commercial operation date of February 18, 2031. The project is being developed within the Pacific Gas & Electric (PGAE) service area. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CA
County
Solano
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Lambie 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LAMBGT1_7_B1
- POI Substation
- Lambie Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about BRUSHY