HIGH WINDS STORAGE
120.62 MW storage in Solano, CA · In queue since April 2021 · Proposed COD March 2031
120.62 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
9y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-03-16
The High Winds Storage project is a proposed 120.62 MW battery storage project located in Solano County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-1850, with an entry date of April 15, 2021. The proposed commercial operation date is March 16, 2031. The project's interconnection status is currently in the System Impact Study phase.
The High Winds Storage project is interconnected with Pacific Gas and Electric (PGAE) at the Birds Landing 230 kV point of interconnection. The development has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Solano
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Birds Landing 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SHILOH_7_B1
- POI Substation
- Birds Landing Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.