TOKAY STORAGE
101.888 MW storage in Santa Clara, CA · In queue since April 2021 · Proposed COD March 2030
101.888 MW
Capacity
1
Components
Battery
5y 1m
In Queue
IA Executed
IA Status
COD target: 2030
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2030-03-18
The Tokay Storage project is a proposed 101.89 MW battery energy storage system located in Santa Clara County, California. The project is being developed within the California Independent System Operator (CAISO) region and is interconnected with Pacific Gas & Electric (PGAE). It entered the CAISO queue as queue ID CAISO-1866 on April 15, 2021, and has a proposed commercial operation date of March 18, 2030. The project's interconnection agreement (IA) has been executed.
The Tokay Storage project is listed as having appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Santa Clara
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Santa Teresa 115 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- EDENVALE_1_N004
- POI Substation
- Santa Teresa Substation