HOLMAN
2,281.985 MW hybrid in Monterey, CA · In queue since April 2021 · Proposed COD February 2034
2,281.985 MW
Capacity
2
Components
Wind + Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2034
Total Duration
12y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2034-02-17
The HOLMAN project is a proposed wind and battery hybrid project located in Monterey County, California. The development project, with a total capacity of 2281.99 MW, consists of a 1525.17 MW wind component and a 756.81 MW battery energy storage system. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1889, with an interconnection queue date of April 15, 2021.
The proposed commercial operation date for the HOLMAN project is February 17, 2034. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Moss Landing 500 kV substation, and the interconnecting utility is PG&E. The project has appeared in recent news coverage related to deals.
Generated from interconnection queue and public data sources
State
CA
County
Monterey
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Moss Landing 500 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about HOLMAN