HARMONY STORAGE 2 (CAISO-1892) — Project Summary

Queue ID
CAISO-1892
Capacity
307.878 MW
Technology
Battery
Status
active
Location
Contra Costa, CA
Region
CAISO
Developer
IA Status
System Impact Study

HARMONY STORAGE 2

CAISO-1892BetaActiveBatteryCAISOLBNL + Live

307.878 MW storage in Contra Costa, CA · In queue since April 2021 · Proposed COD June 2031

307.878 MW

Capacity

1

Components

Battery

5y 1m

In Queue

System Impact Study

IA Status

COD target: 2031

Status
as of 22 months ago
Latest milestoneconstruction startESS News · 2024-07-22
Expected CODQ4 2025ESS News · 2024-07-22
Interconnection

Total Duration

10y 2m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-06-05

About

The Harmony Storage 2 project is a proposed 307.88 MW battery storage project located in Contra Costa County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1892, with a queue entry date of April 15, 2021. The proposed commercial operation date is June 5, 2031. The project's interconnection status is currently in the System Impact Study phase.

The project, which interconnects to the PG&E utility grid at the Contra Costa PP 230 kV point of interconnection, has been the subject of recent news coverage, with three articles appearing in industry, deals, and development publications.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Contra Costa

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

PGAE

Entity

CAISO

Service Type

Point of Interconnection

Contra Costa PP 230 kV

Data Source

LBNL + Live

DeveloperHarmony EnergyESS News · 2024-07-22
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_NP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
CCOSTA_2_B1
POI Substation
Contra Costa Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (1)Beta

Last updated 2026-03-26

View all articles

No ask pi reports yet for this entity.

ask pi about HARMONY STORAGE 2