OAKDALE STORAGE
102.672 MW storage in Stanislaus, CA · In queue since April 2021 · Proposed COD September 2029
102.672 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
8y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-18
The proposed OAKDALE STORAGE project is a 102.67 MW battery energy storage system located in Stanislaus County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1895, with a queue entry date of April 15, 2021. The proposed commercial operation date is September 18, 2029.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Cottle 230 kV substation. Recent news coverage has highlighted the project, focusing on grid-related aspects.
Generated from interconnection queue and public data sources
State
CA
County
Stanislaus
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Cottle 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- COTTLE_7_N002
- POI Substation
- Cottle Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about OAKDALE STORAGE